How to organise a trail marathon
A trail marathon needs more than a marked route and a start line. Begin by securing the course, permits and start and finish locations, then build the safety, timing and volunteer plan around them. Registration and participant communication should follow once the route details are stable. In the final week, check the weather, starting list, medical information, supplies and water stations so race day is spent managing the course rather than fixing preventable gaps.
The plan, step by step
Every task with its own sub-checklist, in the order you'll actually need them.
Preparations
- 1
Apply for competition permit
- 2
Record trail route
2 people
- 3
Check the route for accessibility
3 people
- 4
Reserve start and finish location
- 5
Apply for traffic measures
- 6
Reserve toilets
- 7
Arrange first aid staffing
- 8
Reserve timekeeping
- 9
Check insurance
- 10
Publish the participants page
- 11
Send invitations
2 people
- 12
Open registration
- 13
Process registrations
2 people
- 14
Collect dietary requirements
- 15
Recruit volunteers
2 people
- 16
Assign volunteers
- 17
Check the starting list
2 people
- 18
Order race numbers
- 19
Collect medical information
2 people
- 20
Check the weather forecast
- 21
Send participant letter
- 22
Print the route map
2 people
- 23
Pick up groceries
3 people
- 24
Lay out bib numbers
3 people
- 25
Restock water stations
6 people
- 26
Prepare route signs
3 people
- 27
Check first aid kits
2 people
- 28
Charge batteries and battery packs
2 people
Event
- 29
Open venue
2 people
- 30
Build the start arch
4 people
- 31
Build the finish arch
4 people
- 32
Set up tables and tents
6 people
- 33
Block off the start area
4 people
- 34
Cord off the finish area
4 people
- 35
Place route arrows
8 people
- 36
Place kilometer markers
4 people
- 37
Set up water stations
8 people
- 38
Install time tracking
3 people
- 39
Test sound system
2 people
- 40
Set up the first aid station
3 people
- 41
Set up the cloakroom
3 people
- 42
Staff the registration desk
4 people
- 43
Hand out race numbers
4 people
- 44
Collect bags
3 people
- 45
Guide participants to the starting pen
4 people
- 46
Give the start briefing
2 people
- 47
Start the competition
4 people
- 48
Staff traffic posts
10 people
- 49
Staff route checkpoints
12 people
- 50
Direct participants onward
8 people
- 51
Refill drinks
6 people
- 52
Restock fruit and snacks
4 people
- 53
Register finishers
4 people
- 54
Present medal
3 people
- 55
Welcome finishers
3 people
- 56
Serve the hot meal
6 people
- 57
Serve coffee and tea
3 people
- 58
Settle drink bills
2 people
- 59
Check results
2 people
- 60
Carry out award ceremony
4 people
- 61
Receive the last participants
3 people
Aftercare
- 62
Remove route arrows
8 people
- 63
Remove traffic materials
4 people
- 64
Complete bag distribution
3 people
- 65
Wash dishes
4 people
- 66
Collect waste
6 people
- 67
Clean the venue
6 people
- 68
Take down tents and tables
6 people
- 69
Store equipment safely
3 people
- 70
Return borrowed materials
2 people
- 71
Take waste to the collection point
2 people
- 72
Publish results
- 73
Share participant photos
- 74
Handle lost property
What to bring
Grouped the way you'd shop for it, with quantities.
Furniture
- Party tentsqty 4
- Registration tablesqty 4
- Catering tablesqty 8
- Folding chairsqty 40
- Bar stoolsqty 6
- Waste binsqty 12
- Coat racksqty 3
Sports equipment
- Start arch
- Finish arch
- Route arrowsqty 120
- Kilometer markersqty 43
- Barrier tapeqty 12
- Bib numbersqty 350
- Race bib strapsqty 350
- Finish medalsqty 350
- Starting area barriersqty 20
- Crowd barriersqty 30
- Course tapeqty 20
- Collapsible water bowlsqty 10
- Water bottle cratesqty 20
- Clipboardsqty 15
- Pensqty 50
- Whistlesqty 20
Equipment
- Time registration system
- Laptopqty 2
- Tabletsqty 6
- Walkie-talkiesqty 20
- Mobile phonesqty 6
- Mobile sound system
- Microphonesqty 2
- Extension cordsqty 6
- Power stripsqty 6
- Power banksqty 8
- Charging cablesqty 12
Lighting
- LED work lightsqty 8
- String lightsqty 6
- Headlampsqty 20
First aid
- First aid kitsqty 4
- Thermal blanketsqty 30
- Ice packsqty 20
- Disposable glovesqty 100
- Bandagesqty 200
- Athletic tapeqty 20
Tableware
- Reusable cupsqty 500
- Reusable platesqty 350
- Reusable cutleryqty 400
- Coffee cupsqty 150
- Thermos flasksqty 12
Kitchen
- Coolersqty 12
- Coolersqty 8
- Serving jugsqty 20
- Serving spoonsqty 12
- Cutting boardsqty 6
- Kitchen knivesqty 6
- Serving traysqty 12
- Food containersqty 20
Cleaning
- Trash bag holdersqty 12
- Bucketsqty 6
- Mopsqty 6
- Broom setsqty 4
- Cleaning spongesqty 12
- Hand soap dispensersqty 8
- Disinfectantqty 4
Administration
- Participant listsqty 20
- Route mapsqty 400
- Volunteer badgesqty 50
- Pen holdersqty 8
- Wristbandsqty 400
Catering
- Groceries
Tips
- Record the full trail route early and check it for accessibility, crossings and points where runners could miss a turn. Print the route map and place arrows and kilometre markers only after the final course inspection.
- Apply for the competition permit and traffic measures before opening registration. Allow at least 6–8 weeks for approvals, especially if the course uses public roads or needs crowd barriers.
- Plan one named volunteer for each water station, junction and start or finish duty, plus a small reserve team. Give every team a route section, a phone or walkie-talkie and a clear reporting time.
- Close registration with enough time to order bib numbers, collect medical and dietary information, and publish a final starting list. Send the participant letter no later than 7 days before the race with parking, start times, route and safety instructions.
- Count water, cups or bottles and groceries by station rather than as one total. Recheck the forecast 48 hours before the start, then restock each station and confirm first-aid and timing staff on the final briefing.
Frequently asked questions
- How long does it take to organise a trail marathon?
- Allow at least 3–6 months for a first edition. Permits, traffic measures, insurance, venue reservations and volunteer recruitment should start before registration opens, ideally 8–12 weeks ahead.
- How many volunteers do you need for a trail marathon?
- The number depends on the route, but plan one volunteer at each water station and major junction, plus teams for registration, start, finish, first aid and course marking. Add a reserve group of roughly 10% so absences do not leave a post uncovered.
- When should trail marathon registration close?
- Close registration at least 7–14 days before race day if you need to order bib numbers and prepare a checked starting list. A later closing date is possible only if your supplier and timing system can handle late entries.
- When should you mark a trail marathon course?
- Do a full route check 1–2 weeks before the race, then place the final arrows, tape and kilometre markers shortly before the event. Inspect the course again on race morning because weather, maintenance or other trail users can remove markings.
Plans a lot like this one
Start this plan in Lizzt
Every task and item on this page, ready in your own event. Invite people, split the work, and see who has done what.
Organize this event for free with LizztOrganize for free and invite your contacts!