Power plant open day checklist
A power plant open day needs more than a tour route and a few demonstrations. You need to control visitor numbers, separate public areas from operational hazards, brief every guide and make the arrival process clear. Work through the plan in sequence: confirm the date and capacity, design the route, assess risks, arrange registrations and catering, then test the site and equipment before visitors arrive. This checklist covers the practical details that are often left until the last day.
The plan, step by step
Every task with its own sub-checklist, in the order you'll actually need them.
Preparations
Set the date and program
2 people
Determine visitor capacity
2 people
Develop the tour route
3 people
Identify safety risks
3 people
Prepare safety instructions
2 people
Publish access rules
Send invitations
2 people
Process registrations
2 people
Collect dietary requirements
Send visitor information
Calculate catering quantities
2 people
Reserve catering and groceries
Check restroom facilities
Brief guides
3 people
Assign volunteers
2 people
Prepare the parking route
2 people
Test technical demonstrations
3 people
Check presentations
2 people
Prepare name badges
2 people
Print visitor lists
Print route signs
2 people
Receive deliveries
2 people
Set up non-perishable supplies
2 people
Chill drinks
2 people
Inspect the venue in advance
3 people
Set up tent and tables
4 people
Set up chairs and queue lines
3 people
Set up the reception desk
2 people
Build the catering buffet
3 people
Set up a coffee and tea station
2 people
Set up equipment and screens
3 people
Check lighting and cables
2 people
Place route and safety signs
3 people
Place barriers and gates
3 people
Set up PPE distribution point
2 people
Check the tour rooms
3 people
Welcome presenters
2 people
Briefing with all staff
4 people
Event
Start visitor registration
3 people
Welcome visitors
2 people
Explain the program
Guide the first tour
3 people
Provide technical demonstration
2 people
Answer questions at info point
2 people
Serve coffee and tea
2 people
Serve snacks
3 people
Refill drinks
2 people
Keep buffet and tables clean
2 people
Lead the second tour
3 people
Guide the third tour
3 people
Handle evening presentation
2 people
Guide visitor flow
3 people
Check toilets periodically
Empty trash bins during the event
2 people
Inform last visitors
2 people
Aftercare
Close the distribution points
3 people
Switch off equipment
3 people
Secure visitor registration
Collect tableware and glassware
3 people
Clean up catering
3 people
Sort and remove waste
3 people
Clean the venue
3 people
Dismantle furniture
4 people
Remove signs and barriers
3 people
Inventory materials
2 people
Return borrowed items
2 people
Store leftover stock
2 people
Process registration details
Register lost and found items
Collect invoices and receipts
What to bring
Grouped the way you'd shop for it, with quantities.
Furniture
- Party tentsqty 2
- Folding tablesqty 10
- Chairsqty 80
- High tablesqty 6
- Tableclothsqty 12
- Bollardsqty 12
- Queue barriersqty 10
Equipment
- Laptopsqty 3
- Screensqty 3
- Projector
- Projection screen
- Portable speakersqty 2
- Wireless microphonesqty 2
- Extension cordsqty 8
- Power stripsqty 8
- Cable traysqty 12
- Power banksqty 4
Safety
- Safety helmetsqty 40
- Safety gogglesqty 40
- Hearing protectionqty 40
- Safety vestsqty 20
- Barrier tapeqty 6
- First aid kitsqty 3
- Flashlightsqty 6
- Fire extinguishersqty 4
Communication
- Walkie-talkiesqty 8
- Name badgesqty 80
- Clipboardsqty 8
- Pensqty 30
- Visitor badgesqty 400
- Information leafletsqty 400
- Floor plansqty 250
- Program flyersqty 300
- Route signsqty 20
- Info panelsqty 12
- Visitor listsqty 8
Tableware
- Reusable coffee cupsqty 150
- Reusable drinking cupsqty 250
- Platesqty 180
- Forksqty 180
- Knivesqty 180
- Spoonsqty 180
- Coffee potsqty 4
- Teapotsqty 3
- Serving plattersqty 12
- Serving spoonsqty 12
Kitchen
- Kettlesqty 3
- Coffee machinesqty 2
- Coolersqty 6
- Cutting boardsqty 4
- Kitchen knivesqty 4
- Pliersqty 8
- Serving spoonsqty 8
- Thermos flasksqty 6
- Ice packsqty 24
Decorations
- Buntingqty 10
- Balloonsqty 100
- Balloon weightsqty 10
- Table décorqty 12
Lighting
- LED lampsqty 12
- Outdoor string lightsqty 4
Cleaning
- Waste binsqty 12
- Waste sorting binsqty 4
- Vacuum cleanerqty 2
- Mopsqty 3
- Bucketsqty 3
- Cleaning clothsqty 20
- Broom setsqty 3
Catering
- Groceries
Tips
- Set the visitor capacity before sending invitations. Base it on the size of each tour group, the number of guides and the safe capacity of entrances, restrooms and viewing areas—not only on the total site area.
- Walk the full visitor route at least once before the event and mark every point where visitors need instructions, barriers, lighting or protective equipment. Include the route from parking and registration through to the final exit.
- Send visitor information several days before the open day, including arrival time, parking instructions, access rules, footwear or clothing requirements and any restrictions on photography. This prevents the registration desk from answering the same questions repeatedly.
- Test every technical demonstration, presentation and screen before setup day. Check extension cords, power strips, cable trays, microphones and portable speakers together so a missing connection is found before visitors are on site.
- Prepare the arrival pack in advance: print the visitor list, sort name badges, place pens and clipboards at registration, and give guides a current contact method such as walkie-talkies. Chill drinks only after deliveries and storage space have been checked.
Frequently asked questions
- How far in advance should you plan a power plant open day?
- Start the main planning at least 8 to 12 weeks before the event. Set the date, visitor capacity and tour route first; invitations, registrations, catering and safety communication depend on those decisions.
- How do you manage safety at a power plant open day?
- Complete a route-specific risk review before invitations are sent, then turn the findings into clear access rules and visitor instructions. Brief guides and volunteers at least 1 hour before opening, and check barriers, helmets, goggles, hearing protection and emergency equipment on site.
- How much catering do you need for a power plant open day?
- Calculate quantities from confirmed registrations, not from the number of invitations. Collect dietary requirements before placing the order, then add a small buffer—around 5 to 10 percent—so late arrivals or minor changes do not leave people without food or drinks.
- What should be checked on the morning of a power plant open day?
- Inspect the venue, route signs, parking route, restrooms, registration area and safety controls before the first visitors arrive. Allow at least 2 hours for setup and final testing, including demonstrations, presentations, microphones and visitor communications.
Plans a lot like this one
Start this plan in Lizzt
Every task and item on this page, ready in your own event. Invite people, split the work, and see who has done what.
Organize this event for free with LizztOrganize for free and invite your contacts!