How to organise a cabin building week

A cabin building week needs more than timber and a group of willing builders. Start by fixing the programme, checking the grounds and confirming what permissions are needed. Then secure the wood delivery, map the construction areas and assign volunteers before invitations go out. In the final week, focus on tool checks, safe material storage, water points, waste collection and clear information for parents or participants. This order prevents deliveries, registrations and safety checks from becoming last-minute problems.

The plan, step by step

Every task with its own sub-checklist, in the order you'll actually need them.

Preparations

  • 1

    Set the date and program

    2 people

  • 2

    Check the venue and grounds

    2 people

  • 3

    Arrange permits and notifications

    2 people

  • 4

    Prepare safety plan

    2 people

  • 5

    Create site map

    2 people

  • 6

    Reserve wood delivery

    2 people

  • 7

    Arrange waste collection

  • 8

    Send invitations

    2 people

  • 9

    Process registrations

    2 people

  • 10

    Collect dietary requirements

  • 11

    Assign volunteers

    2 people

  • 12

    Send parent information

    2 people

  • 13

    Check permissions

    2 people

  • 14

    Check first aid supplies

  • 15

    Inventory tools

    2 people

  • 16

    Label tools

    2 people

  • 17

    Check wood for safety

    3 people

  • 18

    Sort and stack wood

    4 people

  • 19

    Mow and level the grounds

    3 people

  • 20

    Mark construction zones

    3 people

  • 21

    Put up barriers

    3 people

  • 22

    Set up tents and tables

    4 people

  • 23

    Place coolers and water points

    3 people

  • 24

    Set up decorations and signage

    3 people

  • 25

    Do the shopping

    3 people

  • 26

    Chill drinks

    2 people

  • 27

    Prepare snacks and lunch

    4 people

  • 28

    Set up the registration table

    2 people

Event

  • 29

    Give safety instructions

    3 people

  • 30

    Assign children to construction teams

    4 people

  • 31

    Distribute building materials

    5 people

  • 32

    Supervise hut building

    12 people

  • 33

    Distribute water and fruit

    3 people

  • 34

    Serve dinner

    6 people

  • 35

    Refill drinks

    2 people

  • 36

    Securely close off the construction site

    4 people

  • 37

    Support the evening program

    6 people

  • 38

    Do end-of-day closeout and handover

    3 people

  • 39

    Replenish construction supplies

    5 people

  • 40

    Brief construction teams again

    4 people

  • 41

    Continue building huts

    12 people

  • 42

    Inspect workstations

    4 people

  • 43

    Provide the lunch break

    4 people

  • 44

    Serve dinner

    6 people

  • 45

    Refill drinks

    2 people

  • 46

    Run the game program

    6 people

  • 47

    Securely close off the construction site

    4 people

  • 48

    Reinforce huts

    12 people

  • 49

    Hand out cabin decorations

    3 people

  • 50

    Provide lunch and drinks

    5 people

  • 51

    Inspect the cabins technically

    4 people

  • 52

    Serve dinner

    6 people

  • 53

    Refill drinks

    2 people

  • 54

    Supervise movie night

    5 people

  • 55

    Prepare cabins for painting

    8 people

  • 56

    Distribute painting materials

    3 people

  • 57

    Decorate and paint huts

    12 people

  • 58

    Prepare the Jury Route

    3 people

  • 59

    Serve dinner

    6 people

  • 60

    Refill drinks

    2 people

  • 61

    Guide hut presentations

    6 people

  • 62

    Handle prize ceremony

    4 people

  • 63

    Inspect huts before the final day

    4 people

  • 64

    Guide the final activities

    8 people

  • 65

    Take souvenir photos

    2 people

  • 66

    Serve the final meal

    6 people

  • 67

    Lead the closing program

    6 people

  • 68

    Ensure children are picked up safely

    5 people

  • 69

    Collect tools

    5 people

Aftercare

  • 70

    Collect waste

    5 people

  • 71

    Wash dishes and supplies

    4 people

  • 72

    Take down tents and tables

    6 people

  • 73

    Carefully dismantle the huts

    10 people

  • 74

    Sort and remove the wood

    6 people

  • 75

    Clean the grounds

    6 people

  • 76

    Clean tools

    4 people

  • 77

    Count and store materials

    3 people

  • 78

    Take waste to the collection point

    3 people

  • 79

    Return borrowed materials

    2 people

  • 80

    Clear away leftover stock

    2 people

  • 81

    Leave venue clean

    3 people

  • 82

    Send participant photos

  • 83

    Handle lost and found

What to bring

Grouped the way you'd shop for it, with quantities.

Furniture

  • Party tentsqty 4
  • Foldable tablesqty 12
  • Folding chairsqty 80
  • Beer tablesqty 8
  • Waste binsqty 10
  • Storage cabinetsqty 4

Construction materials

  • Scaffold planksqty 350
  • Wooden polesqty 180
  • Wooden panelsqty 100
  • Palletsqty 50
  • Corrugated Sheetsqty 80
  • Rope rollsqty 24
  • Nailsqty 25
  • Screwsqty 20
  • Wood glueqty 12

Tools

  • Hammerqty 30
  • Hand sawqty 20
  • Screwdriver setqty 12
  • Cordless drillqty 8
  • Drill bitsqty 8
  • Spirit levelsqty 8
  • Measuring tapesqty 15
  • Combination pliersqty 15
  • Work glovesqty 100
  • Safety gogglesqty 60
  • Wire cuttersqty 10
  • Hand wheelbarrowsqty 4

Safety

  • First aid kitsqty 3
  • Crowd control barriersqty 20
  • Warning signsqty 12
  • Conesqty 30
  • Flashlightsqty 20
  • Reflective vestsqty 25

Tableware

  • Reusable cupsqty 120
  • Reusable platesqty 100
  • Reusable cutleryqty 120
  • Storage cratesqty 20

Kitchen

  • Coolersqty 8
  • Food warmersqty 6
  • Cutting boardsqty 8
  • Chef’s knives and bread knivesqty 12
  • Serving spoonsqty 12
  • Scissorsqty 8
  • Water jugsqty 12
  • Thermos flasksqty 8

Equipment

  • Kettlesqty 4
  • Refrigeratorsqty 2
  • Extension cordsqty 8
  • Power stripsqty 8
  • Portable music speakersqty 2

Lighting

  • LED string lightsqty 12
  • Work lightsqty 8
  • Batteriesqty 40

Decorations

  • Buntingqty 12
  • Bannersqty 6
  • Paintbrushesqty 40
  • Paint traysqty 20
  • Acrylic paintqty 30
  • Markersqty 40
  • Colored paperqty 20
  • Staplersqty 10
  • Rolls of tapeqty 20
  • Apronsqty 40

Sports equipment

  • Footballsqty 6
  • Tennis ballsqty 20
  • Hoopsqty 12
  • Skipping ropesqty 12
  • Cones for gamesqty 30

Cleaning

  • Broomqty 6
  • Dustpanqty 4
  • Mopsqty 6
  • Bucketsqty 8
  • Cleaning clothsqty 30

Catering

  • Groceries

Tips

  • Set the date and daily programme before opening registrations. Include arrival and departure times, working hours, meal breaks and a clear finish time so volunteers and parents know what to expect.
  • Check the venue and grounds at least 4 weeks before the build. Confirm access for the wood delivery, level areas for tents and tables, construction zones, storage space and where waste collection vehicles can reach the site.
  • Reserve the wood delivery before sending final invitations, then check the load when it arrives. Sort and stack scaffold planks, poles, panels, pallets and sheets by type, and remove damaged or unsafe pieces before building starts.
  • Assign volunteers by responsibility, not just by day. Have named people for registration, tool control, first aid, water points, waste and construction supervision, with a backup for each role.
  • Complete the safety setup before participants arrive: mark construction zones, place barriers and warning signs, check first aid kits, and label tools. Keep gloves and safety goggles at the tool point instead of expecting everyone to bring them.

Frequently asked questions

How far in advance should I plan a cabin building week?
Start at least 8 weeks before the first building day. Use the first 2 weeks for the date, venue, permissions and safety plan, then arrange materials, registrations and volunteers before the final site preparations.
When should I order the wood for a cabin building week?
Reserve the wood delivery at least 4 weeks in advance, or earlier if the supplier has limited delivery slots. Check and stack the materials as soon as they arrive, ideally no later than 2 days before construction begins.
How many volunteers do I need for cabin building week?
Plan one responsible adult or experienced supervisor for every 6 to 8 builders, plus separate people for first aid, registration and site logistics. Add at least 2 backup volunteers to cover illness and breaks.
What should I do on the day before cabin building starts?
Finish the site setup 1 day beforehand: mow and level the grounds, mark construction zones, put up barriers, set out tents and tables, place water points and check every tool. Keep the first aid supplies and emergency information easy to find.